Home   -  Northern Region   -  Events   -  Project exibition

Project exibition

  1. ”œImproving the socio-economic situation of disadvantaged communities an area in North Development Region by building a branch of the Soroca-Balti aqueduct to the city of Drochia”

Applicant

Project Location

Total Sum of the Project

NFRD Funding(%)

Duration of project implementation

District Council of Drochia

 

Districts of  Drochia,  Sîngerei, and Florești

99709380 lei

94723910 lei, which is 95% of the total cost of the project

18 months

  2. ”œCenter for Creative Innovation "Pro Career" in the city of Otaci district Ocnita”

Applicant

Project Location

Total Sum of the Project

NFRD Funding(%)

Duration of project implementation

Mayor's Office of Otaci

North Region, Otaci, district of Ocnița 

 

22222872,00 lei

22222872,00 lei, Which is 100% of the total cost of the project

12 months

 

  3. ”œThe renovation of the sector of the L-20 road in Briceni-Grimăncăuți to the border of Ukraine”

Applicant

Project Location

Total Sum of the Project

NFRD Funding(%)

Duration of project implementation

District Council of Briceni

 

North Region, district of Briceni

34 015 630 lei

34 015 630 lei, which is 100% of the total project cost

24 months

  4. ”œInfrastructure rehabilitation of roads leading to International Customs points from Briceni and Larga, in the Briceni district”

Applicant

Project Location

Total Sum of the Project

NFRD Funding(%)

Duration of project implementation

Mayor's office of Briceni

 

North Region, district of Briceni, communities: Larga,Cotiujeni, Grimăncăuți

 

24144390 lei

22908200 lei, Which is 94,88% of the total cost of the project

12 months

 

  5. ”œLocal road construction for the village of Flămînzeni in the district Sîngerei for improved delivery of quality sanitation services”

Applicant

Project Location

Total Sum of the Project

NFRD Funding(%)

Duration of project implementation

Mayor's Office of Coșcodeni, district of Sângerei

 

North Region,  Coșcodeni, Flămânzeni, district of Sângerei

 

1 852 410,00 lei

1 722 730 lei, which is 93% of the total cost of the project

8 months

 

  6. ”œCompletion of the construction of the Prut-Fălești aqueduct, a necessary step for providing drinking water to 76 localities in the North Region”

Applicant

Project Location

Total Sum of the Project

NFRD Funding (%)

Duration of project implementation

District Council of Fălești

 

North Region, districts of Fălești, Ungheni, Glodeni and Bălți 

 

20483858,38 lei

14585000 lei, Which is 71,2% of the total cost of the project

18 months

 

  7. ”œDrinking water supply and sewerage of localities near the Prut River”

Applicant

Project Location

Total Sum of the Project

NFRD Funding (%)

Duration of project implementation

District Council of Glodeni

 

North Region, district of Glodeni

66288000 lei

6388980 lei, which is 96% of the total cost of the project

24 months

 

  8. ”œDrinking water and sanitation for the inhabitants of the villages Risipeni and Bocșa and creating possibilities for future access for social and cultural institutions for 9 other localities in the Fălești and Ungheni districts”

Applicant

Project Location

Total Sum of the Project

NFRD Funding (%)

Duration of project implementation

Mayor's Office of Risipeni district of Fălești

Districts of the North Region including: Fălești and Ungheni, locations: Risipeni, Bocșa, Izvoare, Taxobeni, Grubna, Horești. Lucăceni, Unteni, Scumpia, Stolniceni and Cioropcani 

32 313 490 lei

30 513 490 lei, which is 94% of the total cost of the project

 

24 months

 

  9. ”œCreating improved conditions for supply of drinking water and sanitation for the inhabitants of the villages Parcani, Ocolina, and Rădi Cereșnovăț in the district of Soroca”

Applicant

Project Location

Total Sum of the Project

NFRD Funding (%)

Duration of project implementation

Mayor's Office of Parcani, district of Soroca

 

North Region a R.M., district of Soroca, locations: Parcani - (Voloave), Ocolina - (Å¢epilova)  and Redi Cereșnovăț

27674220,00 lei

27105480,00 lei, Which is  97,94 % of the total cost of the project

24 months

  10. ”œBeekeeping ”“ a successful model for the development of rural areas in the North Region of the Republic of Moldova”

Applicant

Project Location

Total Sum of the Project

NFRD Funding (%)

Duration of project implementation

North RDA

North Region

 

4 975 619,00 lei

4975 619,00 lei

24 months

 

  11. ”œCreating the Business Center in the village of Badiceni”

Applicant

Project Location

Total Sum of the Project

NFRD Funding (%)

Duration of project implementation

Mayor's Office of Bădiceni, district of Soroca

 

North Region, district of Soroca, Bădiceni

3 794 677 lei

3 700 500 lei, which is 97.52% of the total cost of the project

12 months

  12. ”œConnecting the Edineț Industrial Park to public infrastructure and utilities”

Applicant

Project Location

Total Sum of the Project

NFRD Funding (%)

Duration of project implementation

Mayor's Office of Edineț

 

North Region, district ofEdineț, city of Edineț

9791380 lei

9791380 lei, which is 100% of the total project cost

24 months

 

  13. ”œSupporting the development of the north region´s industrial sector through the rehabilitation and upgrading of water and sanitation infrastructure for the Industrial Park on the territory of Răut S.A., in the municipality of Bălți”

Applicant

Project Location

Total Sum of the Project

NFRD Funding (%)

Duration of project implementation

Mayor's Office of Bălți

 

North Region, Bălți

 

15.200.000 lei

14.440.000 lei, which is 95% of the total cost of the project

18 months

 

  14. ”œSupport for private sector development and increased investment in the North Region by building water supply and sewerage for subzone nr. 3 at the Free Economic Zone Bălți”

Applicant

Project Location

Total Sum of the Project

NFRD Funding (%)

Duration of project implementation

Mayor's Office of Bălți

 

North Development Region of the Republic of Moldova: city of Bălți, district Râșcani

15.592.430 lei

14.820.000 lei, which is 95% of the total cost of the project

18 months

 

  15. ”œCreating a solid waste management system in 8 localities of the Glodeni and Fălești districts”

Applicant

Project Location

Total Sum of the Project

NFRD Funding (%)

Duration of project implementation

District Council of Glodeni

 

North Region, Districts of Glodeni and Fălești  

 

5 027 451 lei

5 027 451 lei, which is 100% of the total project cost

18 months

 

  16. ”œA clean environment for a sustainable society”

Applicant

Project Location

Total Sum of the Project

NFRD Funding (%)

Duration of project implementation

Mayor's Office Florești

Florești district

32358875 lei

17682949 lei, which is 54.6% of the project

24 months

 

  17. ”œOutfitting the eco-tourist route Padurea Domnească”

Applicant

Project Location

Total Sum of the Project

NFRD Funding (%)

Duration of project implementation

District Council Glodeni

Glodeni district

 

11552900 lei

5000000 lei, which is 43.3% of the total cost of the project

24 months

  18. ”œGreening the aquatic environment of the Northern Regional Development”

Applicant

Project Location

Total Sum of the Project

NFRD Funding (%)

Duration of project implementation

Mayor's office of Mihăileni, district Râșcani

 

Mihăileni, Riscani (headquartered in the cleaning up of water basins), Northern Region (area of activity of the project)

1800000,00 lei

1800000,00 lei, which is 100% of the total project cost

 

12 months

 

  19. ”œSystem of collection and transport of domestic waste in the micro-region inter-district area of Rîșcani (villages: Singureni, Corlăteni, Grinăuți, Recea, Răcăria, Aluniș) and Drochia (village Pelinia)”

Applicant

Project Location

Total Sum of the Project

NFRD Funding(%)

Duration of project implementation

Mayor's office of Singureni, district Râșcani

 

Inter-district microregion of Râșcani villages: Singureni, Corlăteni, Grinăuți, Recea, Răcăria, Aluniș) - Drochia (Pelinia)

8 217 000 lei

8 217 000 lei, which is 100% of the total project cost

20 months

 

  20. „Restoration of the historical-architectural monument "Conacul Pommer" and the access road to the dendrological Park din the village Țaul, district Dondușeni”

Applicant

Project Location

Total Sum of the Project

NFRD Funding(%)

Duration of the project implementation

City Hall of the villane Țaul, district Dondușeni

Village Țaul, district Dondușeni; Tourist route „Costesti-Pădurea Domnească-Balti-Japca-Soroca-Taul", the route „Criva-Å¢aul-Otaci”

23 305 122,62  lei

23 305,122.62 lei, what constitutes 100% of the total cost of the project

24 months