Home   -  News - Landscaping work was completed for the House of Culture in Băhrinești, Florești

Landscaping work was completed for the House of Culture in Băhrinești, Florești

25.10.2012   4270 views  

BĂHRINEȘTI, FLOREȘTI, October 24, 2012. Landscaping work was completed for the House of Culture in the village of Băhrinești, Florești, for the project "Cultural Crossroads", implemented by the North Regional Development Agency.

For this occasion, a special committee meeting was held to commemorate the completion of work. The commission was made up of Feodosia BUNESCU, Mayor of Băhrinești, chairman; Ion BODRUG, North RDA Director; Constantin BÂNDIU, Head of project management department, Sergiu BOBEICO, chief architect for Florești, and Dorin RUSU, project manager, etc.

The commission of acceptance for the landscaping work for the House of Culture in the village Băhrinești found that 1) The written and drawn parts list document was complete, 2) The List of works contained in the technical documentation was completed, and 3) the work included in the technical documentation was performed according to the project.

Work on the project was performed by SRL "VALIS" under contract by contract number 102, from the 24th July 2012 completed with the North RDA.

The overall objective is the integration of localities Rediul Mare (Dondușeni), Pelinia (Drochia), Alexăndreni (Sîngerei), Rogojeni (Åžoldănești), Negureni (Telenești) and 12 localities of Florești located in Raut Plain, a cultural and regional tourist area.

The amount approved by the National Fund for Regional Development (NFRD) for this project was 1.255,4 MDL. As a result of the project "Cultural Crossroads" the House of Culture in Băhrinești is connected to the power supply and the building´s platform has been paved. For the work "Making planning work for the House of Culture in the village Băhrinești, Florești " 658.964,29 MDL was spent from the NFRD. Also, financed from the NFRD were the following items: furniture, household goods, technical equipment, and computers. Băhrinești  also co-financed the project under the "repair works at the Community Cultural Center," from the Moldova Social Investment Fund with 1.293,2 MDL. Thus, the total budget of the project "Cultural Crossroads" amounted to 2.548,6 MDL.

Bahrinesti City Hall maintains that the deadline for the completion of work on the project is December 2012.